§ 13. Approval of final site development plan.  


Latest version.
  • 1.

    Upon approval of the PIM district and the preliminary site development plan by the board of aldermen, the petitioner shall have 120 days to submit a final development plan for review and approval. The final development plan shall cover the entire area of the approved preliminary development plan.

    2.

    The review of the final site development plan shall follow the same process as the review of the preliminary development plan.

    3.

    The board of aldermen may not approve a final site development plan that differs substantially from the preliminary site development plan. Should such a plan be submitted it shall be reviewed as an amended preliminary site development plan or it shall be rejected.

    4.

    No building, construction or grading permit shall be issued for any element in the project or any phase thereof that does not conform to the approved final site development plan. During the course of construction, no changes shall be made to the final site development plan unless approved by the board of aldermen.

    5.

    If substantial work or construction is not started within one calendar year of the date of the approval of the final site development plan by the board of aldermen, all issued building permits shall terminate, no additional permits shall be issued for the project and the board of aldermen shall hold a public hearing to consider the rezoning of the parcel(s) or any portion thereof to the zoning district classification that existed prior to the approval of the PIM zoning district change.

    6.

    The resumption of issuance of building permits may be authorized and the time limitations specified in this section may be extended by the board of aldermen.

(Ord. No. 2704, § 1, 10-26-98)